STC RAINSBROOK – REFURBISHMENT

MDG were appointed by AECOM to develop proposals for the modification and possible re-role of the secure training centre in Rugby. Whilst in operation a number of Ofsted (and similar) reports were published documenting failures at the Establishment which were pivotal in the closure to children in early 2021. These improvements ranged from the provision […]
HMCTS WOLVERHAMPTON

MDG were appointed by Mott MacDonald to undertake an options feasibility into the provision of works in compliance with updated operational design guidance, provided by HMCTS. The options considered various levels of adjustment based upon a low, medium and high level of investment. These features included aspects covering the following; Wheelchair access Reconfiguration of courtrooms […]
DEFRA (OEP) – ACORN HOUSE

MDG were appointed by Mott MacDonald to provide feasibility layouts for the provision of a new DEFRA department the OEP. The premises were to be located in Worcester within an existing recently refurbishment ground floor. The scope of works was to incorporate the requirements of the OEP as well as provide suitable welfare facilities and […]
DEFRA – HORIZON HOUSE

MDG were appointed by Mott MacDonald to undertake an options appraisal design for the adaption of an existing flagship DEFRA office in Bristol. The purpose of the study was to adapt the current office layout by removing traditional workstations and incorporating areas to encourage individuals to work collaboratively. Conversely, acoustically rated pods were also provided […]
HMP ELMLEY – EXPANSION STUDY

MDG were appointed by Faithful+Gould to initially deliver a feasibility options appraisal on the expansion of the site and provision of an additional 240 places via a new 4 storey houseblock. Following a successful outcome MDG were then invited to develop the proposals into a stage 2 concept design which also included the additional requirements […]
HMP STANDFORD HILL – REDEVELOPMENT

MDG was appointed by Faithful+Gould to develop proposals for the redevelopment of 3no former officer accommodation blocks which date back to when the site was used as an RAF station and target range. The proposal was for the buildings to provide accommodation for risk assessed CAT D prisoners and offer a range of activities to […]
HMP ROCHESTER – ADDITIONAL CAPACITY STUDY

MDG was appointed by Faithful+Gould to undertake a feasibility options appraisal study for the expansion of the existing Establishment in line with the wider Ministry of Justice objectives of providing an additional 10,000 prison spaces within the estate. Upon review a number of options were presented within our report and subsequent presentations to enable the […]
HMP MAIDSTONE – KENT WING REFURBISHMENT

MDG were appointed by Faithful and Gould do develop proposals for the long-term refurbishment of one of the existing wings at the Establishment. Kent wing has suffered from lack of investment and maintenance over the years which has led to the deterioration of the existing internal facilities and structure. A phased solution was chosen to […]
HMP SWALESIDE – IMPROVEMENT OF FACILITIES AND INFRASTRUCTURE

MDG were appointed by Faithful+Gould to provide a full contingent of RIBA stages to assist in the general improvement of facilities and infrastructure at HMP Swaleside, the specific improvement works consisted of the following; Fire Safety Improvements Shower Refurbishment Window Replacement MDG provided a full range of architectural services including acting as Technical Assessors once […]
HMP WHATTON – DEFECT NEGOTIATIONS

Following completion in 2009, the temporary custodial facility (now referred to as Alpha Unit) has suffered inherent issues which have been reported to the MoJ by the prison. The defects vary in complexity and level of disruption they cause. MDG were appointed to assess each issue and report these to the MoJ in order to […]